Mauves sur Loire bridge

informations
Introduction

The rehabilitation of Mauves-sur-Loire bridge consists in substituting the existing deck (3,500 m²) made of brick vaults with a thin deck made of thin precast UHPFRC slabs. The main objective of the project is to upgrade this historic landmark by increasing its bearing capacity and allowing the addition of cantilevered footbridges.

Displayed title

Challenge

Description

This technical challenge was met with the use of Ductal® Infrastructure and the implementation of lightweight precast slabs (with an average thickness of 10 cm), which will reduce the total dead load of the bridge by 50%. In this project, the fibers used were 14 mm/ 0.2 mm steel brass coated.

Displayed title

Optimization

Description

The UHPFRC precast elements were produced at the Delta Prefabrication plant located in Privas (France). Assisted by the Ductal LafargeHolcim technical team, Delta Prefabrication has mastered the several challenges of the project by strictly following the UHPFRC French Standards (NF P18-470 / NF P18-710 / NF P18-451) during the suitability test and then during production control. Particular methods and additional rebar were implemented in order to increase the bonding in the joints between the slabs. Bouygues TPRF/VSL, the general contractor in charge of the project, is responsible for the slab installation and their connection to the structure. The latter was done by in-situ casting the Ductal joint fill solution.

The project was completed in November 2020.

Discover our projects

Displayed title

Dominie Creek

Description

Dominie Creek bridge lies on ancestral territory where Caltrans and Tolowa Dee-ni’ Nation worked together to replace the old dilapidated box culvert structure. The finished bridge has an emblem of spawning salmon at each abutment barrier wall which was inspired by the locations salmon and trout spawning.

Infrastructure

Displayed title

Caderousse Dam

Description

Put into service in 1975, the Caderousse dam is a storage reservoir on the Rhône River in Vaucluse, France.

Infrastructure

Displayed title

SR 141 Over I95

Description

State Route 141 over I95 interchange rehabilitation was commenced in 2019 and expected to be fully completed by Spring 2022. Several crossing structures within this interchange utilized precast panels and required UHPC for all the connections.

Infrastructure

Displayed title

Gardiner Expressway

Description

The Gardiner Expressway structure rehabilitation is part of the City of Toronto’s Strategic Rehabilitation Plan in order to rehabilitate and keep the structure in a safe and operable condition for now and the future.

Infrastructure
Give shape to tomorrow.
Loading
0
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84
85
86
87
88
89
90
91
92
93
94
95
96
97
98
99
100